Update School Street Construction Schedule

Week of 8/20

-Continue work on intersections and curb and gutter

– Remove remainder of pavement West of 8th Street

-Relocate fire hydrant

-Start retaining wall 8/22

-Crack and Seat- Scheduled for 8/20. Will update if subs schedule changes

-Retaining wall work

-Sidewalk/Drives West of 8th Street

-Subgrade Prep/Rock Base Layer

-Utility adjustments within School Street

-Backfill/Grade Site

Week of 8/27

-Grimes Paving Subgrade Trim 8/27

-Grimes Paving Base Layer West of 8th Street.  Currently scheduled for 8/28

-Grimes Paving Surface Course entire project. Currently scheduled for 9/1

-Manhole Adjustments/Pour Back

-Finish up Site Sidewalks

-Backfill/Grade Site

-Pavement Markings

Week of 9/3

-Seeding

-Manhole Lining-Currently scheduled for 9/4. (9/3 is a holiday)